|
Task Fields
These fields appear in the Gantt chart table. Some of them also appear in the Schedules Task Details General Tab , Schedules Task Details Dependencies Tab, Schedules Task Details Resources Tab, Schedules Task Details Project Codes Tab, and the Task Details dialog. Entering data here is the same as entering it there.
Field |
Note |
ID
|
Read only. This is a sequential number assigned by PMWeb. In the Gantt chart table this field is a hyperlink. Left clicking on the link loads the task into the Task Details tabs. Right clicking on the link opens the Task Details dialog.
|
Project
|
Read only. The ID and name of the project to which the task belongs.
|
Schedule
|
Read only. The ID and Name of the schedule to which the task belongs.
|
Code
|
A text field
|
Task
|
The name of the task
|
Start
|
Required. A date less than or equal to Finish. Default is Today
|
Finish
|
A date greater than or equal to Start. If this field is empty the task is referred to as a task milestone. Default is Today
|
%C
|
"Percent Complete". Zero to 100. Default is "0". This represents the physical progress of the task's work.
|
TF
|
"Total Float". Read only. The number of days the task can be delayed from Start without delaying the completion of the project. Tasks with a total float of "0" are considered to be on the critical path.
|
Duration
|
The number of working days needed to complete the task. Tasks with a duration of "0" are referred to as task milestones. Default is "1".
|
Summary
|
A notational field used to group one or more tasks by a summary designation. To use this field: type an entry in this field and save the Gantt chart. The entry is saved to a list. You can then select this entry on other lines in the schedule.
|
Rem. Duration
|
"Remaining Duration"
If "Link % Complete to Remaining Duration" is unchecked, edits to this field have no effect on any other field and are purely notational.
If "Link % Complete to Remaining Duration" is checked and:
|
WBS
| |
Phase
| |
Location
| |
Baseline Start
|
A date less than or equal to Baseline Finish. Default is empty. If you click the Save as Baseline button, the Start date is automatically copied into this field. This field may also be populated by entering a date.
|
Baseline Finish
|
A date greater than or equal to Baseline Start. Default is empty. If you click the Save as Baseline button, the Finish date is automatically copied into this field. This field may also be populated by entering a date.
|
Original Duration
|
Default is empty. If you click the Save as Baseline button, the Duration is automatically copied into this field. This field may also be populated by entering a number.
|
Completed
|
A checkbox. Default is unchecked. Checking this box automatically sets percent complete to "100".
|
Actual Start
|
Default is empty. If you edit this field, Start is set to equal Actual Start.
|
Actual Finish
|
Default is empty. If you edit this field, Finish is set to equal Actual Finish.
|
Actual Duration
|
Default is Actual Finish minus Actual Start.
|
Early Start Constraint
|
The task will not be allowed to start before the selected Start date.
|
Late Start Constraint
|
The task will not be allowed to start after the selected Start date
|
Early Finish Constraint
|
The task will not be allowed to finish before the selected Finish date.
|
Late Finish Constraint
|
The task will not be allowed to finish after the selected Finish date.
|
Late Start
|
Read only. Calculated as Start plus Total Float.
|
Late Finish
|
Read only. Calculated as Finish plus Total Float.
|
Revenue
|
A notational field to record the expected amount of revenue the task will generate.
|
Cost
|
A notational field to record the expected cost of the task.
|
Curve
|
A system defined drop down list. Choices are:
If revenue or cost numbers, a curve, and a cost code have been entered for one or more tasks, cash flow reports can then be generated from the schedule.
|
Actual Revenue
|
A notational field. If Link % Complete to Actual Costs is checked this is set as Revenue times %C divided by 100.
|
Actual Cost
|
A notational field. If Link % Complete to Actual Costs is checked this is set as Cost times %C divided by 100.
|
Baseline Revenue
|
If you click the Save as Baseline button, the Revenue number is automatically copied into this field. This field may also be populated by typing a number.
|
Baseline Cost
|
If you click the Save as Baseline button, the Cost number is automatically copied into this field. This field may also be populated by typing a number.
|
Actual
|
For future use
|
Resources
|
This field shows all of the resources assigned to the task.
|
Cost Code
|
The cost code linked to the task.
|
Status
|
A system defined drop down list. Choices are:
|
Type
|
A system defined drop down list. Choices are:
|