Change Events

 
Change events can be used to initiate the change order process. A single Change Event record contains one table to gauge the potential budget and revenue impacts of a change and another table to track potential cost impacts. Change events can begin by being generated from Online Change Requests. Change event lines can be linked to Contract COs and Commitment COs.
 
Please note that change events are not required to process changes: Contract COs and Commitment COs can be created directly, without first creating change events.
 
Change Events
1

CONTROL PANEL

1. CONTROL PANEL
 
2

BREADCRUMBS BAR

2. BREADCRUMBS BAR
 
3

HEADER TOOLBAR

3. HEADER TOOLBAR
 
4

RECORD TABS

4. RECORD TABS
 
5

HEADER

5. HEADER
 
 
  • Project Field - Required
  • Record # Field - Required. An alphanumeric ID for the record
  • Source Record Field - Read only. If the change event was generated from another record, that record is shown here.
  • Requested Field - Company Field
  • Change Request Field - You can manually link this record to a change request by selecting it from this dropdown list. If you use the Generate button in the Online Change Request this field will automatically be filled in. Click the field label to navigate to the linked record.
  • Risk Analysis Field - You can manually link this record to a risk analysis by selecting it from this dropdown list. If you use the Generate button in the Risk Analysis this field will automatically be filled in. Click the field label to navigate to the linked record.
  • Effective Date Field - Date Field
  • Change Request # Field - Enter a number here. If the change event was generated from an Online Change Request, that record number shows here.
  • Date Field - Read only. The date the record was created.
  • Project Budget Field - Read only. The grand total of the project budget field in the budget table.
  • Owner Budget Field - Read only. The grand total of the owner budget field in the budget table.
  • Ext. Cost Field - Read only. The grand total of the ext. cost field in the cost table.
  • Days Field - Read only. The grand total of the days field in the cost table.
6

BUDGET TABLE TOOLBAR

6. BUDGET TABLE TOOLBAR
 
8

COST TABLE TOOLBAR

8. COST TABLE TOOLBAR
 
 
  • Add Linked Button - Use this button to create new lines in the cost section that are linked to a line in the Change Events Details Tab Budget Table:
 
  • Click one line in the budget table to select it
  • Click the Add Linked Button
  • A new line appears in the cost table opened for editing. The Linked Budget Line field and Description are pre-filled for you.
 
Note: This button only works if exactly one line is selected in the budget table.
9

COST TABLE

9. COST TABLE