Schedules Task Details Dependencies Tab

 
Schedules Task Details Dependencies Tab
 
This tab contains two sections: Predecessors and Successors. The same data entry techniques are used in both sections.
 
One task can contain many predecessors and successors - although they more usually contain only one of each at most - and they can be tasks in the current schedule or in another schedule.
 
1

Project

1. Project
Select a project. This selection filters the Schedule drop down list. The default is the project of the current schedule.
2

Schedule

2. Schedule
Select a schedule. This list is filtered by the Project field. The default is the current schedule.
3

Task

3. Task
Select a task. This list is filtered by the Schedule field.
4

Depend. Type

4. Depend. Type
Select a Dependency Type:
 
  • Finish-To-Start(FS) (the default)
  • Finish-To-Finish(FF)
  • Start-To-Finish(SF)
  • Start-To-Start(SS)
5

Lag

5. Lag
Enter the number of days of lag Lag may be a positive or negative number. Negative lag is sometimes called "lead". The default is "0".