1

Project* Field

1. Project* Field
Required. Project Field.
2

Commitment* Field

2. Commitment* Field
Required. Commitment Field. Click the hyperlink to navigate to the record.
3

Company Field

3. Company Field
Read only. The company of the selected commitment.
4

Type Field

4. Type Field
5

Record #* Field

5. Record #* Field
Required. Enter an alphanumeric ID for the record.
6

Description Field

6. Description Field
7

Currency Field

7. Currency Field
8

Post As Field

8. Post As Field
This is a system list. The choices are:
 
  • Original Scope
  • Revised Scope (the default)
9

Revision Field

9. Revision Field
10

Status Field

10. Status Field
11

Change Request Field

11. Change Request Field
This dropdown list displays Online Change Requests linked to the selected commitment. If you generate the commitment change from the online change request this field is pre-filled. Click the field label to navigate to the record.
12

Cause Field

12. Cause Field
13

Requested By Field

13. Requested By Field
14

Category Field

14. Category Field
15

Reference Field

15. Reference Field
16

Assigned To Field

16. Assigned To Field
17

Change Order Date Field

17. Change Order Date Field
18

Effective Date Field

18. Effective Date Field
19

Days Field

19. Days Field
20

Original Commitment Amount Field

20. Original Commitment Amount Field
Read only. The grand total of Total Cost and the Days from the selected commitment.
21

Prior Approved Changes Field

21. Prior Approved Changes Field
Read only. The grand total of the Total Cost field and the sum of the Days field on all other commitment COs for the selected commitment with a status of "Approved".
22

Prior Revised Contract Field

22. Prior Revised Contract Field
Read only. Original Commitment Amount plus Prior Approved Changes.
23

Total of This Change Field

23. Total of This Change Field
Read only. The grand total of Total Cost and Days from this commitment change order.
24

Contract to This Change

24. Contract to This Change
Prior Revised Contract plus Total of This Change